{"id":4716,"date":"2019-05-21T11:54:42","date_gmt":"2019-05-21T06:24:42","guid":{"rendered":"http:\/\/reconnectenergy.com\/blog\/?p=4716"},"modified":"2019-05-21T11:54:42","modified_gmt":"2019-05-21T06:24:42","slug":"haryana-announces-its-final-dsm-regulations-for-wind-and-solar-2019","status":"publish","type":"post","link":"https:\/\/reconnectenergy.com\/haryana-announces-its-final-dsm-regulations-for-wind-and-solar-2019\/","title":{"rendered":"Haryana announces its final DSM regulations for wind and solar, 2019"},"content":{"rendered":"
Haryana Electricty Regulatory Commission<\/span> announced<\/span><\/a> the DSM regulations for wind and solar, 2019 along with the statement of reasons recently post the draft discussion paper in 2018. The summary of the regulations is as below:<\/span> Regulation to be applicable on:<\/b> Revisions:<\/b><\/p>\n Key points:<\/b><\/p>\n Inter- & Intra-state deviation settlement transactions: <\/b><\/p>\n Deviation Charges for Intra-state sale of power<\/b><\/p>\n <\/a><\/p>\n Deviation Charges for Inter-state sale of power<\/b><\/p>\n <\/a><\/p>\n Deviation charges for under- or over-injection for intra-state transmission and selling\/consuming power outside Haryana<\/b><\/p>\n Deviation Charges in case of under-injection<\/b><\/p>\n <\/a><\/p>\n Deviation Charges in case of over-injection<\/b><\/p>\n
\nTitle<\/b>: Haryana Electricity Regulatory Commission (Forecasting, Scheduling and Deviation Settlement and related matters for Solar and Wind Generation) Regulations, 2019. <\/span>
\nApplicability:<\/b><\/p>\n\n
\n
\nRegulations will apply to all Wind and Solar Energy Generators in Haryana connected to a particular Pooling Sub-Station, or that of an individual Generator connected to some other Sub-Station not be less than <\/span>1 MW<\/b> to the Intra-State Transmission \/Distribution System, including those connected through Pooling Sub-Stations, and using the power generated for self-consumption or sale within or outside the State \u00a0combined installed capacity of the Solar or Wind Generators.<\/span>
\nDeviation Accounting:<\/b> The deviation accounting will be carried out based on the Available<\/span>
\nCapacity:-\u00a0<\/a><\/span>
\nPoint of forecasting:<\/b> Pooling sub-stations and \/or Intra-state transmission\/distribution system.<\/span>
\nAggregation<\/b>: No provision of Aggregation, unlike AP and Karnataka where it is allowed.<\/span>