2. Wheeling of power for Captive Use
a. In Case of wheeling of power to consumption site at 66 kV voltage level and above, normal open access charges and losses as applicable to normal open access consumer.
b. ?In case the injection of power is at 66 kV or above and drawl is at 11 kV, normal transmission charges and losses are applicable; however 50% of wheeling charges and 50% of distribution losses of the energy fed into the grid as applicable to normal open access consumers.
3.Wheeling of power to more than one locations
Wind power projects owners , who decide to wheel electricity for captive use / third party sale , to more than one location, shall pay 5 Paisa/KWh on energy fed in the grid to the distribution company concerned in addition to transmission charges and losses, as applicable.
4. Energy Metering
5.Banking of Surplus Wind Energy
As promotional measure, it is proposed to continue the banking facility for 1 billing cycle for the wind power captive projects wheeling electricity for own use.
Tariff for Biomass power plants, for which Power Purchase Agreements (PPA) have been executed under GoR Policy of 1999 and commissioned before 30.09.2008 will be as under:
The commission has also finalized the capital costs for the technology specific projects. For Biomass Gasifier based power plants the capital cost has been fixed at Rs. 457.24 lakh/MW, and for Biogas based power projects it has been determined at Rs. 883.62Lakh/MW.
Other charges payable by the generators:
kVArh charges: Net kVArh drawal by generating plants from the Grid will be billed at 12.50 paise/kVArh w.e.f 01.04.2015 escalated annually at 0.50 paise/kVArh, unless otherwise revised by the Commission by Order.
Transmission & wheeling charges: For third party sale or captive use within or outside the state the wheeling and transmission charges will be recovered as per orders of the commission.
Banking: Banking of energy is allowed at consumer end for only captive consumption within the state. The period of banking will be monthly basis and banking charges at 2% of banked energy would be payable.
The commission order can be accessed here.
]]>