how do you unlock build slot destiny 2 final shape,free slot machine play http://www.slotln.online Mon, 24 Feb 2020 08:25:41 +0000 en-US hourly 1 https://wordpress.org/?v=5.8.1 http://www.slotln.online/wp-content/uploads/2021/09/cropped-maroonsym-32x32.png APTRANSCO – REConnectEnergy http://www.slotln.online 32 32 APTRANSCO proposes amendments to the APERC DSM regulations for wind and solar http://www.slotln.online/aptransco-proposes-amendments-to-the-aperc-dsm-regulations-for-wind-and-solar/ Mon, 24 Feb 2020 08:25:41 +0000 http://www.slotln.online/blog/?p=4900 In a recent development, the Transmission Corporation of Andhra Pradesh has submitted a proposal, suggesting amendments in the present APERC (Forecasting, Scheduling and
Deviation Settlement of Solar and Wind Generation Regulation, 2017) which is effective since 01.07.2018 for levying and collection of deviation charges from Qualified Coordinating Agencies (QCA).
A report was submitted by the APSLDC describing the issues faced by them & the state distribution companies and has requested amendments to the above-stated regulations as fit suitable to them.
Views/Objections/Suggestions are invited from all stakeholders on the subject on or before 04.03.2020. The original regulation clauses and suggested changes are below:

This would have the following impact:

  • May significantly increase the liability of DSM charges on the Generators.
  • Cause various operational, legal and commercial problems due shift from Aggregate to PSS level forecast, as most Generators may now opt for changing their QCAs, and will result in a major operational exercise for the SLDC as well.
  • Having just the Day Ahead forecast will lead to major deviations in itself. This will not meet the regulatory objective of having lesser variations from RE, which is otherwise possible with Intra Day revisions, that is currently allowed in the Regulation.

Andhra Pradesh Electricity Regulatory Commission has organised a Public Hearing 10th March 2020 (Tuesday) at 10.30hrs in the court hall of APERC in Hyderabad.
 

]]>
APERC unveils wheeling, transmission & SLDC charges for FY15 http://www.slotln.online/aperc-unveils-wheeling-transmission-sldc-charges-for-fy15/ Mon, 19 May 2014 11:02:06 +0000 http://www.slotln.online/blog/?p=1841 The state regulator of AP has determined open access charges namely – wheeling, transmission and SLDC charges for 3rd control period (i.e. from FY15 to FY19).

Wheeling Charges:

The wheeling charges determined by APERC are different for all discoms. The wheeling charges will be effective 17th May 2014. The table below shows the applicable wheeling tariff for subsequent years starting FY15.

Wheeling charges to be levied by CPDCL –

A conventional generator using distribution network of CPDCL and drawing energy at 33 kV will now have to pay Rs. 0.01 per unit. For 11 kV the same will be approx. Rs. 0.195 per unit in FY15.

Wheeling charges to be levied by EPDCL –

Wheeling charges to be levied by NPDCL –

Wheeling charges to be levied by SPDCL –

Note – As per Govt. of AP policy there will be no wheeling charges applicable on non-conventional energy generators (Wind, Solar and Mini-Hydel).?

The order on wheeling tariff can be accessed here.

Transmission Charges:

The APTRANSCO will levy the following transmission charges starting from FY15.

Note – RE generators will continue to be exempted from paying the above transmission tariffs as per Govt. of AP policy directives.?

Transmission tariff order can be read in detail by clicking here.

SLDC Charges:

The following SLDC charges (Annual Fee & Operating Charges) shall be paid by?Generating Companies (including Captive Generating Plants), Distribution?Licensees and Trading Licensees using the intra-State Transmission Network.

Detailed order is available here.

]]>