MOP WAIVERS TRANSMISSION CHARGES AND LOSSES ON ELECTRICITY FROM SOLAR SOURCES

This is an attempt to encourage solar and wind ?energy in the country, the Ministry of Power (MoP) had waived off the inter-state transmission charges and losses on the electricity generated by wind and solar sources of energy in September last year. That order has now been amended by the MoP ?and as per the new order, transmission charges and losses are wavered off only on solar projects. ?The MoP, after consultation with MNRE, CEA, CERC and POSOCO, has notified the following:
For generation projects based on solar resources, the waiver will be on projects commissioned till 31/12/2019. The waiver will be available till 25 years of date of commissioning of such projects and on solar ?projects entering PPAs for sale of electricity to DISCOMs for compliance of RPO. The remaining of the terms and conditions remain the same as the 2016 order.
As per our analysis, this order by the MoP has a number of limitations. First of all, it is only applicable to solar projects from which the electricity will be sold to the DISCOMs. Secondly, it will only be on those solar projects entering PPAs for the compliance of RPO.
The order released in 2016 can be accessed here.