In order to cater the new issues related to energy-mix and large procurement by distribution licensee, earlier mechanisms are further extended to hydro power power and battery energy storage along with thermal and renewable energy. This would ultimately benefit the distribution licensee to meet their RPO within the existing contract capacity and without any additional financial burden.
Applicability of the projects:
Following three types of projects will be eligible under the scheme:
According to MoP, All new and existing coal/lignite/gas based thermal generating stations or hydro power stations are considered as a ‘generating station’ for the purpose of this scheme.
How would the tariff of RE power plants be determined?
Concession on Transmission Charges
In case of RE power plant located within or located in the vicinity of a generating station, No additional transmission charges will be levied.
In case RE power plant situated at one generating station supplying to procurers of another generating station located at different locations and owned by the same generating company, No transmission charge will be levied for using Interstate transmission system(ISTS).
Scheduling and commercial mechanism
Once the schedule for next day is received from the generating station, the generating company can use thermal/hydro and RE Power to meet the scheduled generation. Sum of all the power supplied from thermal/hydro and RE will be considered for DSM purposes.
Important point to note is that the scheduled capacity of the thermal/hydro will be with respect to the PPA agreement and availability of primary fuel and can not be based on the availability of RE power.
The tariff at which the RE power (with or without Energy storage system) supplied to the beneficiaries will be less than ECR (Energy change rate) of the originally scheduled generating station.
The net saving realised under this scheme will be passed on to the beneficiary by the generating company in the ratio of 50:50 subject to the cap of 7 paise/ kWh to the generator.
DSM and Scheduling
As per the scheme, once the schedule for a specific thermal/hydro generating station has been received, then depending upon the forecast available for RE, the generating station will supply to meet the schedule from thermal/hydro power and replacement of RE power.
The deviation will be applicable to the scheduled generation from thermal/hydro stations and sum of actual generation from thermal/hydro and RE power sources. In case the generating station is able to meet its scheduled generation by supplying thermal/hydro and RE power in any ratio, No DSM charge will be applicable.
Additional mechanism for RE bundling
Year
|
Solar RPO
|
Non Solar RPO |
Total RPO
|
||
HPO | Other Non Solar RPO | Total Non Solar RPO | |||
2019-20 | 7.25% | – | 10.25% | 10.25% | 17.50% |
2020-21 | 8.75% | – | 10.25% | 10.25% | 19.00% |
2021-22 | 10.50% | 0.18% | 10.50% | 10.68% | 21.18% |
2022-23 |
To be specified later
|
0.35% |
To be specified later
|
To be specified later
|
To be specified later
|
2023-24 | 0.66% | ||||
2024-25 | 1.08% | ||||
2025-26 | 1.48% | ||||
2026-27 | 1.80% | ||||
2027-28 | 2.15% | ||||
2028-29 | 2.51% | ||||
2029-30 | 2.82% |
Compliance Rules:?
For Solar RPO; The compliance to the extent of 85% and above, remaining shortfall, if any, can be met by excess non solar energy consumed beyond specified Non solar RPO for that particular year.
For Non Solar RPO; the compliance to the extent of 85% and above, remaining shortfall, if any, can be met by excess solar energy or eligible hydro energy consumed beyond specified? solar RPO or HPO for that particular year.
Similarly, For HPO; the compliance to the extent of 85% and above, the remaining shortfall, if any, can be met by excess solar energy or other non solar energy consumed beyond specified solar RPO or Non solar RPO for that particular year.?
It is important to note that for the compliance of HPO, CERC is going to develop the Hydro energy certificate mechanism. To ensure HPO compliance under this mechanism, it would have a capping price of INR 5.50/unit of electrical energy w.e.f. 8th March 2019 to 31st March 2021 with 5% of? annual escalation.
As per the government order dated? 8th March 2019, Large hydro power projects having capacity of more than 25 MW (LHPs) which come into operation after 08.03.2019? will be considered for Hydro power purchase obligation(HPO) within Non Solar Renewable Purchase Obligation(RPO).
Final order can be accessed here.
The Wind Association insisted that the graded incentive will prove to be a balance in the ever-increasing cost with high penetration of RE into the grid.
The Centre Electricity Regulatory Commission in their third amendment (REC regulations) had introduced a vintage multiplier eligible to all the solar generating companies registered under REC framework prior 1 st January 2015 and till 31st March 2017 and amended the regulations to included eligibility criteria for Discoms under REC mechanism for over-achievement of RPO.
CERC was in sync with the suggestion and felt that the DISCOMs need some encouragement for procuring renewable power beyond Renewable Purchase Obligation and the proposed multiplier would help in reducing the financial burden of DISCOMs as they integrate higher share of renewable energy.
However, as per CERC, the step-up REC multiplier that keeps increasing for every 1% RPO over achievement is on the higher side.
Hence, CERC has been requested by Ministry of Power through its office memorandum to revise the third amendment to the REC regulations (December 2014) and make the discoms eligible for 2 RECs for each MWh renewable power procured after achieving the 2% more than the RPO of the corresponding year.
The commission stated that the cost of renewable energy has been on the higher side in the previous years and it has now come to a reasonable level. Even when the costs were high, it was mandated in the National Tariff Policy (NTP) to purchase the costly renewable energy in order to take care of the environment issue related to electricity generation. Hence, the Commission felt that the DISCOMs argument that the higher cost of renewable energy will, in turn, affect the electricity was not a legitimate reason for not complying with the RPO obligation.
The commission is of the opinion that the utility can purchase REC to meet their RPO in case there is no availability of renewable energy sources in the state. The state cannot limit its options within itself and look for options as this is a national level cause and is meant to serve a bigger purpose. Hence, the commission disqualified the plea of DISCOMs that renewable energy sources in Delhi are in deficit.
The contention of the petitioner that the RPO targets are not specified before commencing of the year was canceled as the percent of RPO obligation for the respective financial year is given in the RPO regulations and it becomes the DISCOMs responsibility to fulfill this target in a systematic way. Further, the commission also canceled the plea of financial inadequacy being a reason for the insufficient purchase of RPO and pointed out that the DISCOMs need to manage their finances through equity and loan not only for RPO targets but also for other activities of their distribution business.
The commission in its tariff order announced in August 2017 had disallowed 10% of the cost of REC for underachieving of RPO targets by BYPL & BRPL. The 10% disallowance will only be to the discoms once they meet their RPO.
The defaulting DISCOMs post all the discussions were liable to pay a penalty in the following manner:
*TPDDL complied to its RPO for FY 13-14, FY 14-15 & FY 15-16 on 22.02.2017, 25.10.2017 & 29.11.17 respectively.
*BRPL & BYPL did not comply with its RPO continuously for three consecutive years. Deadline till 5th August 2019 was given to make the payment.?
* Rs. 5000 per day penalty is calculated into the no. of days of delay made by the DISCOM
Apart from the above-specified penalty, an individual penalty of INR 1,00,000 was imposed on each DISCOM for FY 2013-2014,& FY 2014-2015 for the failure of meeting their RPO. The respondent Discoms are directed to pay the penalty amount within a month’s time.?
Delhi is the second state to have penalized its DISCOMs over non-compliance of RPO. earlier Bihar Regulatory Commission has also penalized its DISCOMs over RPO non-compliance. The State Regulatory Commissions of our country are getting stringent with each passing day over RPO compliance and making sure that the regulations are followed rigorously.
?